HCM completed the design-build shoring for the Azure condominium project in downtown London. Due to the soil conditions encountered during initial drilling, a full depth caisson wall was installed for the construction of a two storey underground parking structure.

A combination of tiebacks and internal struts were used to support the 12.0m deep excavation. After piling was complete tieback encroachment became no longer possible along the west wall and had to be converted to a double rakered system. As the foundation structure was entirely precast this presented unique challenges when using rakers. RWH worked together with HCM and the Developer to make the internal bracing system work around the precast panels and designed the system to allow for removals to help facilitate the constriction process.

The shoring was constructed next to an existing church sensitive to movements. Excavation procedures were modified and extra considerations were taken in both the design and construction to reduce any movements and vibrations. Further, RWH completed target, inclinometer and vibration monitoring to verify the shoring performance throughout construction and ensure minimal impact to the church structure.

Client: The Tricar Group

Location: London, Ontario

Aligning with the HC Group’s core value of sustainability, the Azure project became the first LEEDS condominium project in London’s history.

8 Ida Street

8 Ida Street HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack
Read More
The Bow

The Bow

The future Bow building, located in Calgary, Alberta Canada, is an innovation in both architectural and shoring design. At 58 stories and with a footprint of two city blocks, The
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More
Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast