Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem

Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment.

  • Due to the tight confines of the site and the proximity of exterior walls, columns and footings, the use of a traditional soldier pile and lagging system was not feasible.
  • Instead, a shotcrete shoring and underpinning solution was developed in conjunction with the Owner and the General Contractor.
  • By working with the forming contractor, a zero clearance solution was used as the backside of the new form work.
  • In addition to vertical cut stability, the shotcrete was also designed to provide underpinning stabilization to the undermined column pad footings and exterior wall footings.
  • By placing strategically located vertical mini piles at and around the pad footings, the additional stabilization was achieved.

The use of the shotcrete solution in this application allowed the General Contractor to minimize disturbance and disruption to the ongoing facility operations.

Client: Stucor Construction Ltd
Location: Niagara Falls, Ontario

The Osterberg Cell

The Osterberg Cell HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close
Read More

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
Aldershot GO Station Improvements

Aldershot GO Station Improvements

Our Innovative Solution Saves Time Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The
Read More

Herald Block

Herald Block HCM was chosen to provide a comprehensive design-build shoring solution for Phase 1 of Brookfield Place development, which will become the tallest building in Western Canada. The excavation
Read More
The Bow

The Bow

The future Bow building, located in Calgary, Alberta Canada, is an innovation in both architectural and shoring design. At 58 stories and with a footprint of two city blocks, The
Read More