Skip to content

TTC St. Clair Station

Overcoming Tight Access and High Water Table

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted with some interesting challenges, including extremely tight access and a high water table.

  • The east elevator pit was constructed with a 10 m deep caisson wall, braced horizontally against the existing subway structure. Piles were drilled with a Bauer BG 22H self-lining drill in order to overcome the high groundwater conditions.
  • The west elevator pit was constructed with an 8 m deep lagging wall, the piles for which were drilled in a single weekend in order to comply with TTC and City of Toronto access restrictions.
  • HC Matcon’s excavation operations were aided by our own dewatering systems installed at each elevator pit.
  • A total of 4 deep wells were effectively used to lower the water table below final excavation grade.

Client: Consolidated Canadian

Location: Toronto, Ontario

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More

Odeon Ronmore Development

Odeon Ronmore Development HCM was contracted to provide the design and installation of shoring system for a mixed use commercial development in the main corridor of the Garrison Woods area
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh
Read More