Skip to content

EEEL University of Calgary

Zero Ground Loss

This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for the foundations were almost identical to the previous project, with the installation of approximately 175 cast-in-place belled piles. Again, this new building was a result of the fast-growing population at the University of Calgary and the demand for specialty studies with emphasis on future global trends such as clean energy and the environment.

The soil conditions, which are typical and uniform throughout the mentioned site, consisted mainly of silty sand and clay till which is ideal for large capacity belled piles.

  • The shafts for the piles were predominantly 900mm, 1000mm, and 1,200mm in diameter.
  • The bells were sized at: 2000mm, 2400mm, 2800mm, 3400mm and 3600mm in diameter.

The average founding depth on this project was approximately 13.0m – 17.0m with the need to protect the upper portion of the pile shafts by using temporary casing approximately 8.0m long. The concrete volumes for single piles ranged between 23 – 26 cubic meters. Among the challenges for HCM on this project was installation of piles in close proximity to a concrete utility tunnel. EllisDon approached HCM with a request for shoring and underpinning on a portion of the tunnel.

HCM proposed a design/build tied-back continuous caisson wall method where special consideration was given to the stated goal of zero ground loss from underneath of the tunnel.

Client: EllisDon Corporation
Location: Calgary, Alberta

Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More
HCM Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More
TTC St. Clair Station

TTC St. Clair Station

Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During construction, HC Matcon was confronted withsome interesting
Read More

Pixel by Battistella

Pixel by Battistella HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was
Read More
Paruk Residence

Paruk Residence

Overcoming Poor Soil-Bearing Capacity The Paruk Residence is a high end two story structure, located at 24 York Valley Crescent in North York, Ontario, just north of the Don River.
Read More