St. Thomas Courthouse

Alternate Methods Stop Running Sands

HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction of the proposed shoring was initially for soldier piles and lagging with a single level of bracing using tiebacks.

The existing structures were initially designed using conventional underpinning. When excavation reached the underside of the existing structures it had been determined that soils were not what expected in the geotechnical report. The existing soil conditions were flowing wet sands and HCM was asked to provide an alternate method to the conventional underpinning.

HCM implemented a shotcrete underpinning system including positive support of the existing rubble foundation to allow us to support the structure and lateral pressure of the earth while excavation proceeded to base of the new structure.

With the assistance of RWH (an HC Group of companies) our ability to react and provide an alternate design solution allowed HCM to complete successfully the shoring and foundation works within EllisDon’s budget and schedule.

Client: EllisDon Construction
Location: St. Thomas, Ontario

St. Thomas Courthouse - Shotcrete, Soldier Piles & Lagging

Lakeview Water Treatment Plant

Lakeview Water Treatment Plant This project was part of the second phase of an expansion program to the region of Peel’s Lakeview Water Treatment Plant. Given the information provided at
Read More
Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion The Government of Alberta and Alberta Health Services (AHS) have broken ground on this project, which will renovate and expand the hospital
Read More

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More
Telus Sky tower - HC Matcon

Telus Sky tower

Telus Sky tower The Telus Sky tower will be the 3rd tallest building in Calgary with the deepest basement excavation in western Canada. HCM Group took on the challenge of
Read More

McMaster Nuclear Building

McMaster Nuclear Building The nuclear research building was an upgrade to the existing structure to allow for world class nuclear research for leading nuclear scientists.  This project was funded by
Read More
Bluwater Condominiums

Bluwater Condominiums

The Pemberton Group is adding the luxury waterfront Bluwater Condominiums to its portfolio. The 22,000 SF area of shoring area will accommodate the construction of three eight-story buildings on the
Read More