Paruk Residence

Overcoming Poor Soil-Bearing Capacity

The Paruk Residence is a high end two story structure, located at 24 York Valley Crescent in North York, Ontario, just north of the Don River. A geotechnical investigation performed by Patriot Engineering revealed very poor soil bearing capacity, unsuitable for a slab-on-grade or strip footing foundation.

  • The floor slab was designed as a structural slab supported on grade beams resting on helical pier foundations. The helical piers were 2-7/8 inch diameter, 55 ksi minimum yield strength, galvanized, and supplied by Ideal Group.
  • The helical piers were designed for a maximum 30 kips working load, which was achieved at a torque resistance of approximately 9,000 ft. lbs. Using a 17,000 ft. lbs. McMillen drive unit, 94 piers were installed in 3 days.

HCM also did the excavation, perimeter shotcrete shoring and U/S stone placement c/w geotextile, which helped construction access and provided a clean surface for the concrete form work contractor.

Client: HC Matcon
Location: Toronto, Ontario

 

 

Brantford General Hospital

Brantford General Hospital This innovative project represents the first use of shotcrete shoring in place of caisson walls against a building in Ontario. Caisson walls have typically been utilized duw
Read More

Talbot Street

Talbot Street HCM completed the design-build shoring for the Azure condominium project in downtown London. Due to the soil conditions encountered during initial drilling, a full depth caisson wall was
Read More
St. Joseph's Healthcare Redevelopment Project

St. Joseph’s Healthcare Redevelopment Project

Unique Soil Conditions The future location for this tower is located immediately adjacent to the emergency wing of the existing St. Joseph’s hospital in Hamilton, Ontario. HCM is a recognized
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More

Dufferin Jog Elimination

Dufferin Jog Elimination This project involved the extension of Duffering Street under an existing CN rail line and through the abutment wall of a century old CN bridge at Queen
Read More