Paruk Residence

Overcoming Poor Soil-Bearing Capacity

The Paruk Residence is a high end two story structure, located at 24 York Valley Crescent in North York, Ontario, just north of the Don River. A geotechnical investigation performed by Patriot Engineering revealed very poor soil bearing capacity, unsuitable for a slab-on-grade or strip footing foundation.

  • The floor slab was designed as a structural slab supported on grade beams resting on helical pier foundations. The helical piers were 2-7/8 inch diameter, 55 ksi minimum yield strength, galvanized, and supplied by Ideal Group.
  • The helical piers were designed for a maximum 30 kips working load, which was achieved at a torque resistance of approximately 9,000 ft. lbs. Using a 17,000 ft. lbs. McMillen drive unit, 94 piers were installed in 3 days.

HCM also did the excavation, perimeter shotcrete shoring and U/S stone placement c/w geotextile, which helped construction access and provided a clean surface for the concrete form work contractor.

Client: HC Matcon
Location: Toronto, Ontario

 

 

Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
Centre 10

Centre 10

Centre 10 Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th
Read More

Lakeview Water Treatment Plant

Lakeview Water Treatment Plant This project was part of the second phase of an expansion program to the region of Peel’s Lakeview Water Treatment Plant. Given the information provided at
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More