Paruk Residence

Overcoming Poor Soil-Bearing Capacity

The Paruk Residence is a high end two story structure, located at 24 York Valley Crescent in North York, Ontario, just north of the Don River. A geotechnical investigation performed by Patriot Engineering revealed very poor soil bearing capacity, unsuitable for a slab-on-grade or strip footing foundation.

  • The floor slab was designed as a structural slab supported on grade beams resting on helical pier foundations. The helical piers were 2-7/8 inch diameter, 55 ksi minimum yield strength, galvanized, and supplied by Ideal Group.
  • The helical piers were designed for a maximum 30 kips working load, which was achieved at a torque resistance of approximately 9,000 ft. lbs. Using a 17,000 ft. lbs. McMillen drive unit, 94 piers were installed in 3 days.

HCM also did the excavation, perimeter shotcrete shoring and U/S stone placement c/w geotextile, which helped construction access and provided a clean surface for the concrete form work contractor.

Client: HC Matcon
Location: Toronto, Ontario

 

 

Currie Reservoir

Currie Reservoir

Horizontal Underpinning This project consisted of an interlocking secant pile wall, combined with horizontal underpinning to accommodate a new connection to a pump house at the Currie reservoir in Calgary.
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More
Credit Valley Hospital

Credit Valley Hospital

Alternative to Save Time and Money The Credit Valley Hospital in Mississauga, Ontario is undergoing a massive expansion and renovation. HC Matcon was brought in to undertake the shoring, underpinning,
Read More
Mars B Toronto General Hospital

Mars B Toronto General Hospital

This 3.5 Million dollar contract involved HC Matcon providing a full excavation, a 16,000 Sq. Ft. shoring and large diameter caisson package for this project. Challenges included the support of
Read More

Mapleview Drive

Mapleview Drive The expansion of Mapleview Drive in Barrie required track protection for an existing railway overpass. HCM was retained to install a strutted piles and lagging shoring system. RWH
Read More