Skip to content

Mount Royal University Conservatory

Mount Royal University Conservatory

Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for structural & geotechnical engineering consisted of local firms of Read Jones Christoffersen Ltd. & Thurber Engineering Ltd. The need for the new addition to a campus was a result of fast growing student population at the Mount Royal University and demands for specialty studies.

The soil conditions at mentioned site consisted predominantly of clay till which is ideal for large capacity belled piles. The shafts for the piles were in the range of:

  • 900mm
  • 1000mm
  • 1200mm
  • 1370mm in diameter.

The bells were sized at:

  • 2000mm
  • 2400mm
  • 2800mm
  • 3400mm
  • 3600mm in diameter

 

Mount Royal University Conservatory - Soldier Piles & Lagging

The average basing depth on this project was approx. 12.0m – 15.0m with an occasional need to protect the upper portion of the pile shafts by using temporary steel caising in order to prevent ingress of water into the pile shafts. The average concrete volumes for single piles were approx. 20 – 24 cu. metres. Among the challenges for HCM was installation of piles in close proximity to concrete and steel underground utilities which were present on site as a result of previously demolished structure. In many cases this required coring and managing voids in the shafts after removal of these obstructions. Also, numerous piles were belled in soils with occurrence of large boulders which required special considerations for handling of equipment, customized tooling requirements and operating skills.

HCM finished foundation piling scope of work ahead of planned schedule.

Client: Cana Management
Location: Calgary, Alberta

Aldershot GO Station Improvements

Aldershot GO Station Improvements

Our Innovative Solution Saves Time Work at the Aldershot Go Station in Burlington, Ontario comprised of the construction of two new pedestrian tunnels to access the existing passenger platforms. The
Read More
Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More
HCM Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More
Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario
Read More
Great Lakes Copper Plant

Great Lakes Copper Plant

Great Lakes Copper Plant The Great Lakes Copper Plant in London, Ontario, posed a technical challenge in shotcrete shoring. HC Matcon helped to facilitate the installation of a new copper
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More