Skip to content

Mount Royal University Conservatory

Mount Royal University Conservatory

Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for structural & geotechnical engineering consisted of local firms of Read Jones Christoffersen Ltd. & Thurber Engineering Ltd. The need for the new addition to a campus was a result of fast growing student population at the Mount Royal University and demands for specialty studies.

The soil conditions at mentioned site consisted predominantly of clay till which is ideal for large capacity belled piles. The shafts for the piles were in the range of:

  • 900mm
  • 1000mm
  • 1200mm
  • 1370mm in diameter.

The bells were sized at:

  • 2000mm
  • 2400mm
  • 2800mm
  • 3400mm
  • 3600mm in diameter

 

Mount Royal University Conservatory - Soldier Piles & Lagging

The average basing depth on this project was approx. 12.0m – 15.0m with an occasional need to protect the upper portion of the pile shafts by using temporary steel caising in order to prevent ingress of water into the pile shafts. The average concrete volumes for single piles were approx. 20 – 24 cu. metres. Among the challenges for HCM was installation of piles in close proximity to concrete and steel underground utilities which were present on site as a result of previously demolished structure. In many cases this required coring and managing voids in the shafts after removal of these obstructions. Also, numerous piles were belled in soils with occurrence of large boulders which required special considerations for handling of equipment, customized tooling requirements and operating skills.

HCM finished foundation piling scope of work ahead of planned schedule.

Client: Cana Management
Location: Calgary, Alberta

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More

Odeon Ronmore Development

Odeon Ronmore Development HCM was contracted to provide the design and installation of shoring system for a mixed use commercial development in the main corridor of the Garrison Woods area
Read More
Smith Residence

Smith Residence

Toronto’s First Permanent Soil Nail Wall This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in
Read More
TTC Wilson Complex Modification

TTC Wilson Complex Modification

Engineering Solutions The Toronto Transit Commission will be purchasing all new subway cars in the near future, creating the requirement of larger maintenance carhouses. The original contract drawings employed caisson
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More