Skip to content

Mount Royal University Conservatory

Mount Royal University Conservatory

Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for structural & geotechnical engineering consisted of local firms of Read Jones Christoffersen Ltd. & Thurber Engineering Ltd. The need for the new addition to a campus was a result of fast growing student population at the Mount Royal University and demands for specialty studies.

The soil conditions at mentioned site consisted predominantly of clay till which is ideal for large capacity belled piles. The shafts for the piles were in the range of:

  • 900mm
  • 1000mm
  • 1200mm
  • 1370mm in diameter.

The bells were sized at:

  • 2000mm
  • 2400mm
  • 2800mm
  • 3400mm
  • 3600mm in diameter

 

Mount Royal University Conservatory - Soldier Piles & Lagging

The average basing depth on this project was approx. 12.0m – 15.0m with an occasional need to protect the upper portion of the pile shafts by using temporary steel caising in order to prevent ingress of water into the pile shafts. The average concrete volumes for single piles were approx. 20 – 24 cu. metres. Among the challenges for HCM was installation of piles in close proximity to concrete and steel underground utilities which were present on site as a result of previously demolished structure. In many cases this required coring and managing voids in the shafts after removal of these obstructions. Also, numerous piles were belled in soils with occurrence of large boulders which required special considerations for handling of equipment, customized tooling requirements and operating skills.

HCM finished foundation piling scope of work ahead of planned schedule.

Client: Cana Management
Location: Calgary, Alberta

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More

Herald Block

Herald Block HCM was chosen to provide a comprehensive design-build shoring solution for Phase 1 of Brookfield Place development, which will become the tallest building in Western Canada. The excavation
Read More
Scarborough Hospital

Scarborough Hospital

A Design-Build Solution The Scarborough Hospital was adding a new Critical Care Centre in the courtyard surrounded on all sides by existing hospital structures.  HC Matcon’s scope of work included:
Read More
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More
Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More

Pixel by Battistella

Pixel by Battistella HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was
Read More