Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used soldier piles and shotcrete lagging shoring (SPLS) with soil nails to support the excavation of an approximately 30-foot deep underground parking garage.

One challenge of this project was the close proximity of the excavation to the property line of the adjacent residential buildings. The consultant’s design included a caisson wall for this part of the system. HC Matcon proposed an alternative to save the owner and general contractor money, schedule time, and square footage of finished building by applying an equivalent system of shotcrete shoring and soil nails. This system will also act as a one-sided form for foundation walls.

During this project, there were some unforeseen obstacles for the shoring installation that required avoidance.

Utilities were found between the shoring system and the adjacent existing building footings to be demolished. HC Matcon was able to modify the pile design to support these utilities during demolition.


Other concrete obstructions were avoided by using an alternative pipe pile design to satisfy property line constraints, a perched walkway for the access of neighboring houses, and to facilitate the demolition of the existing parking garage.

HC Matcon will take on many challenges related to shoring and foundation design while keeping the interests of the general contractor and owner in mind.

Client: Lewis Build Corporation
Location: Toronto, Ontario

Cobourg Railway Station

Cobourg Railway Station On this project, HCM, in conjunction with its in-house engineering company, RWH Engineering Inc. (RWH), was able to offer the owner one source for the design, supply,
Read More
Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion The Government of Alberta and Alberta Health Services (AHS) have broken ground on this project, which will renovate and expand the hospital
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More

Highland Creek WWTP

Highland Creek WWTP Due to increased population and the requirement for treating excess amounts of waste water, Highland Creek WWTP underwent a significant upgrade to provide clean water for the
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More