Skip to content

Upper House Condominiums

Upper House Condominiums

HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring system comprised of piles and lagging with caisson wall adjacent to an existing residence was installed. 

Typical to developments in Toronto, there were encroachment restrictions on the south side of the site which only allowed for the tiebacks to extend a maximum of 6.2m to the neighbouring property line. To work within the limited space restrictions, RWH Engineering Inc. designed a system utilizing an upper row of double splayed anchors. Post-grouted strand anchors were installed to achieve the required load capacity in the soils. HCM with the supervision of RWH completed a load testing program to determine the optimal number of post-grout cycles required to meet the anchor design. Reducing the post-grout cycles resulted in schedule savings to the project.

Further, the shoring design was finite element modelled to allow for comparison against the monitoring results and ensure the shoring performed adequately throughout the construction. 

HCM and RWH worked together to produce a design-build shoring re-design which was tailored to the specific requirements of the project and resulted in cost and schedule savings.

Location: Toronto, ON 

Customer: SKYGRiD Construction Inc.

 

Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More
HC Matcon - Twinning of the West Trunk Sanitary Sewer

Twinning of the West Trunk Sanitary Sewer

Twinning Of The West Trunk Sanitary Sewer This project includes the installation of a deep trunk sanitary sewer within bedrock under Erin Mills Parkway in Mississauga. HCM together with RWH Engineering
Read More

Pixel by Battistella

Pixel by Battistella HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was
Read More
Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More