Skip to content

Upper House Condominiums

Upper House Condominiums

HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring system comprised of piles and lagging with caisson wall adjacent to an existing residence was installed. 

Typical to developments in Toronto, there were encroachment restrictions on the south side of the site which only allowed for the tiebacks to extend a maximum of 6.2m to the neighbouring property line. To work within the limited space restrictions, RWH Engineering Inc. designed a system utilizing an upper row of double splayed anchors. Post-grouted strand anchors were installed to achieve the required load capacity in the soils. HCM with the supervision of RWH completed a load testing program to determine the optimal number of post-grout cycles required to meet the anchor design. Reducing the post-grout cycles resulted in schedule savings to the project.

Further, the shoring design was finite element modelled to allow for comparison against the monitoring results and ensure the shoring performed adequately throughout the construction. 

HCM and RWH worked together to produce a design-build shoring re-design which was tailored to the specific requirements of the project and resulted in cost and schedule savings.

Location: Toronto, ON 

Customer: SKYGRiD Construction Inc.

 

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More

Highland Creek WWTP

Highland Creek WWTP Due to increased population and the requirement for treating excess amounts of waste water, Highland Creek WWTP underwent a significant upgrade to provide clean water for the
Read More
St. Joseph's Health Centre Parking

St. Joseph’s Health Centre Parking

Shotcrete Reduces Costs for Owner The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking. HC Matcon was responsible
Read More

Twinning Tunnels

Twinning Tunnels The installation of a deep trunk sanitary sewer system in the bedrock beneath Erin Mills Parkway in Mississauga required an innovative approach for shoring manholes. For this project,
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More