Skip to content

Upper House Condominiums

Upper House Condominiums

HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring system comprised of piles and lagging with caisson wall adjacent to an existing residence was installed. 

Typical to developments in Toronto, there were encroachment restrictions on the south side of the site which only allowed for the tiebacks to extend a maximum of 6.2m to the neighbouring property line. To work within the limited space restrictions, RWH Engineering Inc. designed a system utilizing an upper row of double splayed anchors. Post-grouted strand anchors were installed to achieve the required load capacity in the soils. HCM with the supervision of RWH completed a load testing program to determine the optimal number of post-grout cycles required to meet the anchor design. Reducing the post-grout cycles resulted in schedule savings to the project.

Further, the shoring design was finite element modelled to allow for comparison against the monitoring results and ensure the shoring performed adequately throughout the construction. 

HCM and RWH worked together to produce a design-build shoring re-design which was tailored to the specific requirements of the project and resulted in cost and schedule savings.

Location: Toronto, ON 

Customer: SKYGRiD Construction Inc.

 

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More

TTC Patten Building

TTC Patten Building HC Matcon was retained to install micropile foundation for TTC Patten Building on 835 Davenport Road, Toronto. The building was originally designed for storage of paper tickets
Read More
Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More
HCM Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More
HC Matcon - Twinning of the West Trunk Sanitary Sewer

Twinning of the West Trunk Sanitary Sewer

Twinning Of The West Trunk Sanitary Sewer This project includes the installation of a deep trunk sanitary sewer within bedrock under Erin Mills Parkway in Mississauga. HCM together with RWH Engineering
Read More