Skip to content

Upper House Condominiums

Upper House Condominiums

HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring system comprised of piles and lagging with caisson wall adjacent to an existing residence was installed. 

Typical to developments in Toronto, there were encroachment restrictions on the south side of the site which only allowed for the tiebacks to extend a maximum of 6.2m to the neighbouring property line. To work within the limited space restrictions, RWH Engineering Inc. designed a system utilizing an upper row of double splayed anchors. Post-grouted strand anchors were installed to achieve the required load capacity in the soils. HCM with the supervision of RWH completed a load testing program to determine the optimal number of post-grout cycles required to meet the anchor design. Reducing the post-grout cycles resulted in schedule savings to the project.

Further, the shoring design was finite element modelled to allow for comparison against the monitoring results and ensure the shoring performed adequately throughout the construction. 

HCM and RWH worked together to produce a design-build shoring re-design which was tailored to the specific requirements of the project and resulted in cost and schedule savings.

Location: Toronto, ON 

Customer: SKYGRiD Construction Inc.

 

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More
Centre 10

Centre 10

Centre 10 Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More
Segmental Excavation Mining and Support of Excavation - Eglinton LRT - Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE The Eglinton LRT Cedarvale Station required the new structure to pass below the existing TTC subway below grade. HC Matcon Inc. (HCM)
Read More