Skip to content

Upper House Condominiums

Upper House Condominiums

HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring system comprised of piles and lagging with caisson wall adjacent to an existing residence was installed. 

Typical to developments in Toronto, there were encroachment restrictions on the south side of the site which only allowed for the tiebacks to extend a maximum of 6.2m to the neighbouring property line. To work within the limited space restrictions, RWH Engineering Inc. designed a system utilizing an upper row of double splayed anchors. Post-grouted strand anchors were installed to achieve the required load capacity in the soils. HCM with the supervision of RWH completed a load testing program to determine the optimal number of post-grout cycles required to meet the anchor design. Reducing the post-grout cycles resulted in schedule savings to the project.

Further, the shoring design was finite element modelled to allow for comparison against the monitoring results and ensure the shoring performed adequately throughout the construction. 

HCM and RWH worked together to produce a design-build shoring re-design which was tailored to the specific requirements of the project and resulted in cost and schedule savings.

Location: Toronto, ON 

Customer: SKYGRiD Construction Inc.

 

Highland Creek WWTP

Highland Creek WWTP Due to increased population and the requirement for treating excess amounts of waste water, Highland Creek WWTP underwent a significant upgrade to provide clean water for the
Read More

Herald Block

Herald Block HCM was chosen to provide a comprehensive design-build shoring solution for Phase 1 of Brookfield Place development, which will become the tallest building in Western Canada. The excavation
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More

Brantford General Hospital

Brantford General Hospital This innovative project represents the first use of shotcrete shoring in place of caisson walls against a building in Ontario. Caisson walls have typically been utilized duw
Read More

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More