The Telus Sky tower will be the 3rd tallest building in Calgary with the deepest basement excavation in western Canada. HCM Group took on the challenge of creating a shoring system suitable for the 30m excavation. RWH designed the shoring system with an 11m deep perched secant wall and shotcrete was used in the bedrock to stabilize the rest of the excavation. HCM contractors were responsible for the installation of the perched secant wall and the shotcrete.

The project was not without its challenges. These challenges included neighboring structures, the LRT system that ran adjacent to the site, existing Telus utilities and limited working space within the excavation. An extremely sensitive Telus duct bank ran adjacent to the excavation and the movement of the bank had to be kept to a minimum. RWH had to take this into consideration when designing the wall. The footprint of the excavation was only 2,100m2. HCM contractors were able to work strategically with other sub-contractors to ensure work could be carried out seamlessly in the small area. RWH provided precision monitoring of the shoring, neighboring structures and the LRT line. Monitoring reports were provided twice a week until the excavation reached sound bedrock and it was then reduced to weekly.

HCM Group were able to use their experience with similar past projects to design and construct a shoring system that was suitable for the 30m excavation. The shoring moved 75% of what was originally predicted, proving it was more than adequate.

Client: Icon West Construction

Location: Calgary, Alberta

HC Group - Telus Sky Shoring Clean Wall
Telus Sky tower - HC Matcon
Telus Sky tower - HC Matcon
Telus Sky tower - HC Matcon

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More
Grand House

Grand House

Difficult But Not Impossible The Grand House is a student designed and constructed co-operative housing project located in Cambridge, Ontario.  It has won awards and is a landmark building. Due
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More
Smith Residence

Smith Residence

Toronto’s First Permanent Soil Nail Wall This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM