Skip to content

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during the excavation for a new retaining wall at the Eglinton LRT project. The 14m (45’) high slope was approximately halfway excavated for a permanent block retaining wall when it a sudden slip failure occurred creating concern for the adjacent properties. RWH designed a slope retention system with soil nails and shotcrete facing to remediate the slope and allow for continued excavation. Using a TEI drill mounted on an excavator, HCM was able to reach the top of slope to install soil nails.  Shotcrete was applied by a nozzleman in an elevated work platform. Once the exposed portion of the failed slope was stabilized, excavation was able to resume and HCM continued installing additional lifts of anchors and shotcrete to the base of the finished slope for a total protected area of 1250m2 (13,500 SF).

HCM and RWH provided an efficient solution, adapting the slope protection design to assist with the durability of the permanent retaining wall. Real-time design changes were made onsite to accommodate additional area required after installation had already commenced, enabling the original retaining wall construction to resume as fast as possible. 

 

Location: Toronto, ON

Customer: Metrolinx

LRT Slope Protection at Retaining Wall
LRT Slope Protection at Retaining Wall
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More

Lakeview Water Treatment Plant

Lakeview Water Treatment Plant This project was part of the second phase of an expansion program to the region of Peel’s Lakeview Water Treatment Plant. Given the information provided at
Read More
Segmental Excavation Mining and Support of Excavation - Eglinton LRT - Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE The Eglinton LRT Cedarvale Station required the new structure to pass below the existing TTC subway below grade. HC Matcon Inc. (HCM)
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More

8 Ida Street

8 Ida Street HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More