Skip to content

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during the excavation for a new retaining wall at the Eglinton LRT project. The 14m (45’) high slope was approximately halfway excavated for a permanent block retaining wall when it a sudden slip failure occurred creating concern for the adjacent properties. RWH designed a slope retention system with soil nails and shotcrete facing to remediate the slope and allow for continued excavation. Using a TEI drill mounted on an excavator, HCM was able to reach the top of slope to install soil nails.  Shotcrete was applied by a nozzleman in an elevated work platform. Once the exposed portion of the failed slope was stabilized, excavation was able to resume and HCM continued installing additional lifts of anchors and shotcrete to the base of the finished slope for a total protected area of 1250m2 (13,500 SF).

HCM and RWH provided an efficient solution, adapting the slope protection design to assist with the durability of the permanent retaining wall. Real-time design changes were made onsite to accommodate additional area required after installation had already commenced, enabling the original retaining wall construction to resume as fast as possible. 

 

Location: Toronto, ON

Customer: Metrolinx

LRT Slope Protection at Retaining Wall
LRT Slope Protection at Retaining Wall
Segmental Excavation Mining and Support of Excavation - Eglinton LRT - Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE

Eglinton LRT – Cedarvale Station SEM and SOE The Eglinton LRT Cedarvale Station required the new structure to pass below the existing TTC subway below grade. HC Matcon Inc. (HCM)
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More
Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More

Spray River Bridge

Spray River Bridge During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As
Read More

144 Park Street

144 Park Street During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo.
Read More

University of Toronto Faculty of Law

TTC Steels Launch Shaft The expansion of the Faculty of Law building at the University of Toronto incorporated the addition of another storey to the existing building. The increased loading
Read More