Love Condos

This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both rakers and tiebacks in order to avoid conflicts with neighboring properties. HCM along with RWH design and constructed the shoring system to meet the project scheduled and owners budget. By using in house engineering HCM was able to respond to changes in of the project quickly and effectively to ensure the project was completed on time.
Included on this project is:

• Pile and lagging walls

• Prestressed soil rock anchors

• Rakers and struts

• Regular monitoring

HCM worked closely with the General Contractor to ensure the shoring systems were built efficiently and as per the designs and specifications. In addition, together we were able to accelerate the overall project schedule.

Client: 59 Project Management
Location: Markham, Ontario

HCM Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More

Sarcee Trail

Sarcee Trail The foundation of an existing residential apartment building in Southwest Calgary was compromised and required remedial measures to be completed. RWH designed a micropile underpinning system based on
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More

Spray River Bridge

Spray River Bridge During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More