Zero Ground Loss

This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for the foundations were almost identical to the previous project, with the installation of approximately 175 cast-in-place belled piles. Again, this new building was a result of the fast-growing population at the University of Calgary and the demand for specialty studies with emphasis on future global trends such as clean energy and the environment.

The soil conditions, which are typical and uniform throughout the mentioned site, consisted mainly of silty sand and clay till which is ideal for large capacity belled piles.

  • The shafts for the piles were predominantly 900mm, 1000mm, and 1,200mm in diameter.
  • The bells were sized at: 2000mm, 2400mm, 2800mm, 3400mm and 3600mm in diameter.

The average founding depth on this project was approximately 13.0m – 17.0m with the need to protect the upper portion of the pile shafts by using temporary casing approximately 8.0m long. The concrete volumes for single piles ranged between 23 – 26 cubic meters. Among the challenges for HCM on this project was installation of piles in close proximity to a concrete utility tunnel. EllisDon approached HCM with a request for shoring and underpinning on a portion of the tunnel.

HCM proposed a design/build tied-back continuous caisson wall method where special consideration was given to the stated goal of zero ground loss from underneath of the tunnel.

Client: EllisDon Corporation
Location: Calgary, Alberta

HCM Group - K2 Condominiums

K2 Condominiums

K2 Condominiums This development on King Street in Waterloo required approximately 15,000 SF of shoring for two levels of underground parking. RWH Engineering Inc. (RWH) designed a piles and lagging
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More
Paruk Residence

Paruk Residence

Overcoming Poor Soil-Bearing Capacity The Paruk Residence is a high end two story structure, located at 24 York Valley Crescent in North York, Ontario, just north of the Don River.
Read More

Oshawa Mall

Oshawa Mall The Oshawa Mall expansion was a large project that required several foundation and shoring services. HCM met the needs of the contractor by providing both tied back and
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both