CN Malton GO Station

Challenge: Build While Trains Are Running

Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.

HC Matcon’s scope of work, includes:

  • 37 caissons at 30-inch diameter, and an approximately 25-foot deep shoring system with strand anchors.
  • The pile and caisson installation was challenging due to a number of factors. The train tracks, in close proximity to the work being done, were required to be fully operational.
  • Special precautions were taken for track protection and the safety of workers.
  • Due to the close proximity to Pearson International Airport, special precautions were taken to conform to the Greater Toronto Airport Authority’s guidelines for the operation of high-mast drills and cranes.
  • HC Matcon accommodated special staging requirements set forth by CN for work, such as the installation of the precast tunnel and track relocations.

HC Matcon will work with all parties involved in a project to ensure a swift execution with minimal conflicts.

Client: B. Gottardo
Location: Toronto, Ontario

Pixel by Battistella

Pixel by Battistella HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was
Read More

Midtown Lofts

Midtown Lofts On this project, HCM in conjunction with RWH Engineering Inc. (RWH), provided the owner with a complete design-build package and precision monitoring services for an 8.5m deep temporary
Read More
Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario
Read More

Sarcee Trail

Sarcee Trail The foundation of an existing residential apartment building in Southwest Calgary was compromised and required remedial measures to be completed. RWH designed a micropile underpinning system based on
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More
St. Joseph's Health Centre Parking

St. Joseph’s Health Centre Parking

Shotcrete Reduces Costs for Owner The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking. HC Matcon was responsible
Read More