Skip to content

144 Park Street

144 Park Street

During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo. HCM was retained by Mady Developments to design, supply, and install a complete 9,500 SF bypass shotcrete shoring system.

RWH Engineering Inc. (RWH), an HC Group company, took on the design and monitoring responsibility for the project. The design consisted of a tied-back bypass shotcrete shoring system to a depth of approximately 5 meters. Bypass shotcrete is a unique solution developed by HCM which combines the benefits of shotcrete with a traditional piling system.

HCM’s design-build approach allows for a single source of responsibility. The HCM/RWH integrated working relationship facilitates quick response to design changes and site issues that may occur, ultimately minimizing potential delays and helping to maintain project milestones.

Client: Mady Development Construction Ltd.

Location: Waterloo, Ontario

The HC Group team is positioned to provide exemplary service when performing design-build work – providing both cost and schedule savings to the project.

Mars B Toronto General Hospital

Mars B Toronto General Hospital

This 3.5 Million dollar contract involved HC Matcon providing a full excavation, a 16,000 Sq. Ft. shoring and large diameter caisson package for this project. Challenges included the support of
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More
Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More
Scarborough Hospital

Scarborough Hospital

A Design-Build Solution The Scarborough Hospital was adding a new Critical Care Centre in the courtyard surrounded on all sides by existing hospital structures.  HC Matcon’s scope of work included:
Read More
Smith Residence

Smith Residence

Toronto’s First Permanent Soil Nail Wall This project involved a hillside lot and a high end home in Toronto. The installation was the first permanent soil nail wall used in
Read More