Skip to content

Maxwell Bates

Maxwell Bates

This project, located on Fourth Street in the downtown core of Calgary, consisted of a tied-back continuous caisson wall.  The caisson wall provided zero ground loss and minimal water infiltration, an important feature in the high density area of downtown.  HCM was able to call upon experience from similar successful past projects, such as the installation of a tied-back continuous caisson wall for the new Mustard Seed Building on Tenth Avenue and Centre Street S.E., to ensure a successful project.

The system was designed for a maximum excavation of approximately 8.5 meters below grade at the north portion of the site and 10 meters below grade at the south portion of the site.  This resulted in an approximate total area of 13,100 square feet of shoring required.

This project is another example of HCM’s ability to work with a General Contractor to execute a successful shoring project with a tight schedule and budget.

Client: Ledcor Construction Ltd.

Location: Calgary, Alberta

Silver Creek Solar Farm

Silver Creek Solar Farm For this project, HCM provided installation services to EllisDon for the helical pile foundations for future solar racking. Due to the stringent timelines and project milestones,
Read More

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh
Read More

Spray River Bridge

Spray River Bridge During the 2013 flooding in Southern Alberta, the Spray River undermined the foundation of a 24m long all season bridge causing the bridge to collapse.   As
Read More
Dufferin Mall

Dufferin Mall

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed
Read More
Great Lakes Copper Plant

Great Lakes Copper Plant

Great Lakes Copper Plant The Great Lakes Copper Plant in London, Ontario, posed a technical challenge in shotcrete shoring. HC Matcon helped to facilitate the installation of a new copper
Read More