This project, located on Fourth Street in the downtown core of Calgary, consisted of a tied-back continuous caisson wall.  The caisson wall provided zero ground loss and minimal water infiltration, an important feature in the high density area of downtown.  HCM was able to call upon experience from similar successful past projects, such as the installation of a tied-back continuous caisson wall for the new Mustard Seed Building on Tenth Avenue and Centre Street S.E., to ensure a successful project.

The system was designed for a maximum excavation of approximately 8.5 meters below grade at the north portion of the site and 10 meters below grade at the south portion of the site.  This resulted in an approximate total area of 13,100 square feet of shoring required.

This project is another example of HCM’s ability to work with a General Contractor to execute a successful shoring project with a tight schedule and budget.

Client: Ledcor Construction Ltd.

Location: Calgary, Alberta

Mount Royal University Conservatory

Mount Royal University Conservatory

Mount Royal University Conservatory Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for
Read More

Midtown Lofts

Midtown Lofts On this project, HCM in conjunction with RWH Engineering Inc. (RWH), provided the owner with a complete design-build package and precision monitoring services for an 8.5m deep temporary
Read More
Credit Valley Hospital

Credit Valley Hospital

Alternative to Save Time and Money The Credit Valley Hospital in Mississauga, Ontario is undergoing a massive expansion and renovation. HC Matcon was brought in to undertake the shoring, underpinning,
Read More
Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More
Mars B Toronto General Hospital

Mars B Toronto General Hospital

This 3.5 Million dollar contract involved HC Matcon providing a full excavation, a 16,000 Sq. Ft. shoring and large diameter caisson package for this project. Challenges included the support of
Read More

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More