8 Ida Street

8 Ida Street

HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack of real-estate and property, the home owners decided to build an in ground pool inside of their newly completed residence.  The residence consisted of an existing crawl space in which the pool was requested.  It should be noted that the interior finishes consisted of sensitive glass and marble which were sensitive to movement below.

The project involved deepening the crawl space for the swimming pool addition.  Innovation was required due to a unique underpinning design which included two layers of continuous rebar within the panel in order for it to be used as a permanent foundation wall.  This created constructability issues due to the required three panel sequences of installation.  To allow for unobstructed panel excavation, HC Matcon and RWH, an HC Group company, special bulkhead steel embedments were fabricated from mesh and anchor couplers (provided by Williams Form Engineering) in the HC Matcon shop. These were used in place of rebar to allow for all threading of the bars satisfying the engineer.

The work was successfully completed on time and on budget.  Underpinning systems are a specialty of HC Matcon.

Client: Laureden Inc.

Location: Toronto, Ontario

HC Matcon - Twinning of the West Trunk Sanitary Sewer

Twinning of the West Trunk Sanitary Sewer

Twinning Of The West Trunk Sanitary Sewer This project includes the installation of a deep trunk sanitary sewer within bedrock under Erin Mills Parkway in Mississauga. HCM together with RWH Engineering
Read More
Upper House Condominiums - Caisson Wall Piles and Lagging

Upper House Condominiums

Upper House Condominiums HCM completed the shoring for the eight storey Upper House Condominium project which required a 12m deep excavation for two levels of underground parking. A tied-back shoring
Read More

Weston Road

Weston Road The Metrolinx Weston Tunnel project will serve as a below grade rail corridor for the GO Georgetown line linking the airport to downtown Toronto. HCM was subcontracted by
Read More
Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More