St. Thomas Courthouse

Alternate Methods Stop Running Sands

HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction of the proposed shoring was initially for soldier piles and lagging with a single level of bracing using tiebacks.

The existing structures were initially designed using conventional underpinning. When excavation reached the underside of the existing structures it had been determined that soils were not what expected in the geotechnical report. The existing soil conditions were flowing wet sands and HCM was asked to provide an alternate method to the conventional underpinning.

HCM implemented a shotcrete underpinning system including positive support of the existing rubble foundation to allow us to support the structure and lateral pressure of the earth while excavation proceeded to base of the new structure.

With the assistance of RWH (an HC Group of companies) our ability to react and provide an alternate design solution allowed HCM to complete successfully the shoring and foundation works within EllisDon’s budget and schedule.

Client: EllisDon Construction
Location: St. Thomas, Ontario

St. Thomas Courthouse - Shotcrete, Soldier Piles & Lagging
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More

Maxwell Bates

Maxwell Bates This project, located on Fourth Street in the downtown core of Calgary, consisted of a tied-back continuous caisson wall.  The caisson wall provided zero ground loss and minimal
Read More
Mars B Toronto General Hospital

Mars B Toronto General Hospital

This 3.5 Million dollar contract involved HC Matcon providing a full excavation, a 16,000 Sq. Ft. shoring and large diameter caisson package for this project. Challenges included the support of
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More