Skip to content

McMaster Nuclear Building

McMaster Nuclear Building

The nuclear research building was an upgrade to the existing structure to allow for world class nuclear research for leading nuclear scientists.  This project was funded by the provincial and federal governments as part of a stimulus package for Hamilton, Ontario.  This project required a deep foundation solution to support the proposed structure next to the existing nuclear building.

Helicals were designed and installed with 4.5” diameter helical pipe to allow for desired corrosion protection.  Load testing confirmed the ULS loading and the design was based on a SLS of 400KN.  RWH, an HC Group company, worked very closely with the structural engineer, Atkinson, to ensure SLS settlements and differentials were less than the specified 1/2” maximum.  The helicals were founded 30ft deep in a layer that provided sufficient resistance but required very accurate placement due to wet, poor soils located just above and below the layer.  An important challenge to note was that construction and excavation was performed beside the nuclear testing building and vibrations had to be kept to a minimum due to sensitive equipment located inside.

HC Matcon’s operators and site supervisors performed their work with a very high degree of skill allowing successful installation of the helicals while proceeding on schedule with the contract timeline.  HC Matcon also provided zero clearance shotcrete complete with excavation in a second stage contract, working with a new owner, to attain budgeted costs allowing that contract to proceed with government grants.  This is also an excellent example of the HCM/RWH service in design build of helical piers.

Client: IRA MCdonald Construction Limited

Location: Hamilton, Ontario

Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More

Twinning Tunnels

Twinning Tunnels The installation of a deep trunk sanitary sewer system in the bedrock beneath Erin Mills Parkway in Mississauga required an innovative approach for shoring manholes. For this project,
Read More

Midtown Lofts

Midtown Lofts On this project, HCM in conjunction with RWH Engineering Inc. (RWH), provided the owner with a complete design-build package and precision monitoring services for an 8.5m deep temporary
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More
Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More

Burke Residence

Burke Residence The site topography presented the challenging task of installing shoring on steep slopes which impeded the accessibility of conventional equipment to the residential lot at the back alley
Read More