Skip to content

McMaster Nuclear Building

McMaster Nuclear Building

The nuclear research building was an upgrade to the existing structure to allow for world class nuclear research for leading nuclear scientists.  This project was funded by the provincial and federal governments as part of a stimulus package for Hamilton, Ontario.  This project required a deep foundation solution to support the proposed structure next to the existing nuclear building.

Helicals were designed and installed with 4.5” diameter helical pipe to allow for desired corrosion protection.  Load testing confirmed the ULS loading and the design was based on a SLS of 400KN.  RWH, an HC Group company, worked very closely with the structural engineer, Atkinson, to ensure SLS settlements and differentials were less than the specified 1/2” maximum.  The helicals were founded 30ft deep in a layer that provided sufficient resistance but required very accurate placement due to wet, poor soils located just above and below the layer.  An important challenge to note was that construction and excavation was performed beside the nuclear testing building and vibrations had to be kept to a minimum due to sensitive equipment located inside.

HC Matcon’s operators and site supervisors performed their work with a very high degree of skill allowing successful installation of the helicals while proceeding on schedule with the contract timeline.  HC Matcon also provided zero clearance shotcrete complete with excavation in a second stage contract, working with a new owner, to attain budgeted costs allowing that contract to proceed with government grants.  This is also an excellent example of the HCM/RWH service in design build of helical piers.

Client: IRA MCdonald Construction Limited

Location: Hamilton, Ontario

CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More
Centre 10

Centre 10

Centre 10 Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th
Read More
The Fuse at Evolution

The Fuse at Evolution

The Fuse at Evolution Following years of planning by the City of Calgary, construction on the anticipated East Village Development has started. The proud owners of the first land deal
Read More
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More

Parkside Dr. Slope Stabilization

Parkside Dr. Slope Stabilization The City of Toronto tendered a slope stabilization project that required the installation of helical piles in the embankment of a failed slope on Parkside Drive
Read More