Skip to content

Lakeview Water Treatment Plant

Lakeview Water Treatment Plant

This project was part of the second phase of an expansion program to the region of Peel’s Lakeview Water Treatment Plant. Given the information provided at the time of tender, HCM proposed the use of shotcrete shoring for the site’s earth retention system. Later, due to an unforeseen influx of water into the excavation from a problematic sand lense and the resulting saturated soil conditions, shotcrete was found to no longer be a suitable solution for the site’s shoring. To address the issue, HCM devised a perched caisson wall system to cut off the flow of groundwater.

As fieldwork progressed, other fill soil conditions were encountered that were different from the geotechnical report issued at the time of tender. A change of the soil conditions, as encountered at Lakeview, would typically impact the project’s schedule because of the need for a redesign of the shoring system. HCM was able to respond with practical solutions to keep the project moving while updating the drawings to represent the design changes.

HCM can overcome most problems or restrictions to produce a final product that is desirable to all parties.

Client: North America Constructors Ltd.

Location: Mississauga, Ontario

Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More
Centre 10

Centre 10

Centre 10 Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th
Read More
HCM Group - Sage Condominiums: Phase II

Sage Condominiums: Phase II

Sage Condominiums: Phase II The construction of the new Sage Condominium required a shoring system that could facilitate the 10 meter foundation depth while working within encroachment restrictions. RWH Engineering
Read More
Scarborough Hospital

Scarborough Hospital

A Design-Build Solution The Scarborough Hospital was adding a new Critical Care Centre in the courtyard surrounded on all sides by existing hospital structures.  HC Matcon’s scope of work included:
Read More
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More