HCM was chosen to provide a comprehensive design-build shoring solution for Phase 1 of Brookfield Place development, which will become the tallest building in Western Canada. The excavation spanned a city block and extended 22 meters deep. The shoring system, designed by RWH Engineering Inc. (RWH), was comprised of an 11 meter deep perched caisson wall above shotcrete, which continued into the rock for the remaining depth of the excavation. 

The challenges faced on this project included old foundations encountered during drilling, surrounding tightly clustered utilities, vulnerable neighbouring structures, and the adjacent light rail transit (LRT) system. HCM met these challenges with close attention to detail and meticulous planning to prevent any utility conflicts and structural damage. RWH completed the precision monitoring of the shoring and adjacent structures providing weekly reports to all stakeholders for the duration of the project. 

Client: EllisDon Corporation

Location: Calgary, Alberta

HCM was able to use their experience on past projects to design and construct a shoring solution that worked with the varying soil conditions at depth. This solution resulted in a more sustainable project as the perched wall required less material than a traditional full depth caisson wall, and provided project cost and schedule savings. Brookfield Place is an example of the ability of the HC Group to work together and overcome challenges in complex projects.

Currie Reservoir - Continuous Caisson Wall

Currie Reservoir – Continuous Caisson Wall

Increased Safety: We Used Horizontal H-Piles This project is a part of a large upgrade to the Currie Reservoir in southwest Calgary, Alberta. The project included the installation of a
Read More

TTC Patten Building

TTC Patten Building HC Matcon was retained to install micropile foundation for TTC Patten Building on 835 Davenport Road, Toronto. The building was originally designed for storage of paper tickets
Read More

Twinning Tunnels

Twinning Tunnels The installation of a deep trunk sanitary sewer system in the bedrock beneath Erin Mills Parkway in Mississauga required an innovative approach for shoring manholes. For this project,
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More
Milton Grade Separation

Milton Grade Separation

Milton Grade Separation Client: BOT Construction Location: Milton, Ontario