HCM was chosen to provide a comprehensive design-build shoring solution for Phase 1 of Brookfield Place development, which will become the tallest building in Western Canada. The excavation spanned a city block and extended 22 meters deep. The shoring system, designed by RWH Engineering Inc. (RWH), was comprised of an 11 meter deep perched caisson wall above shotcrete, which continued into the rock for the remaining depth of the excavation. 

The challenges faced on this project included old foundations encountered during drilling, surrounding tightly clustered utilities, vulnerable neighbouring structures, and the adjacent light rail transit (LRT) system. HCM met these challenges with close attention to detail and meticulous planning to prevent any utility conflicts and structural damage. RWH completed the precision monitoring of the shoring and adjacent structures providing weekly reports to all stakeholders for the duration of the project. 

Client: EllisDon Corporation

Location: Calgary, Alberta

HCM was able to use their experience on past projects to design and construct a shoring solution that worked with the varying soil conditions at depth. This solution resulted in a more sustainable project as the perched wall required less material than a traditional full depth caisson wall, and provided project cost and schedule savings. Brookfield Place is an example of the ability of the HC Group to work together and overcome challenges in complex projects.

144 Park Street

144 Park Street During the bidding process, HCM proposed an innovative design-build shoring solution for the 144 Park Street project, a 19 storey condominium in the downtown core of Waterloo.
Read More
Slope Remediation

Slope Remediation

Slope Remediation HCM and RWH Engineering provided a design build solution to remediate a failing slope at a project located in Western Ontario. Prior to HCM’s involvement, the site was excavated 7m into a
Read More
Guelph Civic Administration Complex

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete
Read More
Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion The Government of Alberta and Alberta Health Services (AHS) have broken ground on this project, which will renovate and expand the hospital
Read More
LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall

LRT Slope Protection at Retaining Wall HC Matcon (HCM) and RWH Engineering (RWH) reacted quickly after being contacted to provide a design-build solution for a slope failure that occurred during
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More