Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for structural & geotechnical engineering consisted of local firms of Read Jones Christoffersen Ltd. & Thurber Engineering Ltd. The need for the new addition to a campus was a result of fast growing student population at the Mount Royal University and demands for specialty studies.

The soil conditions at mentioned site consisted predominantly of clay till which is ideal for large capacity belled piles. The shafts for the piles were in the range of:

  • 900mm
  • 1000mm
  • 1200mm
  • 1370mm in diameter.

The bells were sized at:

  • 2000mm
  • 2400mm
  • 2800mm
  • 3400mm
  • 3600mm in diameter

 

Mount Royal University Conservatory - Soldier Piles & Lagging

The average basing depth on this project was approx. 12.0m – 15.0m with an occasional need to protect the upper portion of the pile shafts by using temporary steel caising in order to prevent ingress of water into the pile shafts. The average concrete volumes for single piles were approx. 20 – 24 cu. metres. Among the challenges for HCM was installation of piles in close proximity to concrete and steel underground utilities which were present on site as a result of previously demolished structure. In many cases this required coring and managing voids in the shafts after removal of these obstructions. Also, numerous piles were belled in soils with occurrence of large boulders which required special considerations for handling of equipment, customized tooling requirements and operating skills.

HCM finished foundation piling scope of work ahead of planned schedule.

Client: Cana Management
Location: Calgary, Alberta

HC Matcon - Twinning of the West Trunk Sanitary Sewer

Twinning of the West Trunk Sanitary Sewer

Twinning Of The West Trunk Sanitary Sewer This project includes the installation of a deep trunk sanitary sewer within bedrock under Erin Mills Parkway in Mississauga. HCM together with RWH Engineering
Read More
Credit Valley Hospital

Credit Valley Hospital

Alternative to Save Time and Money The Credit Valley Hospital in Mississauga, Ontario is undergoing a massive expansion and renovation. HC Matcon was brought in to undertake the shoring, underpinning,
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More

Sarcee Trail

Sarcee Trail The foundation of an existing residential apartment building in Southwest Calgary was compromised and required remedial measures to be completed. RWH designed a micropile underpinning system based on
Read More
St. Thomas Courthouse

St. Thomas Courthouse

Alternate Methods Stop Running Sands HCM was retained to design, supply and install a complete shoring system to facilitate construction of the new St. Thomas Court House for EllisDon. Construction
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More