Design considerations for the foundations were similar to previous projects in the area, with installation of approx. 220 cast-in-place belled piles. The project design team for structural & geotechnical engineering consisted of local firms of Read Jones Christoffersen Ltd. & Thurber Engineering Ltd. The need for the new addition to a campus was a result of fast growing student population at the Mount Royal University and demands for specialty studies.

The soil conditions at mentioned site consisted predominantly of clay till which is ideal for large capacity belled piles. The shafts for the piles were in the range of:

  • 900mm
  • 1000mm
  • 1200mm
  • 1370mm in diameter.

The bells were sized at:

  • 2000mm
  • 2400mm
  • 2800mm
  • 3400mm
  • 3600mm in diameter

 

Mount Royal University Conservatory - Soldier Piles & Lagging

The average basing depth on this project was approx. 12.0m – 15.0m with an occasional need to protect the upper portion of the pile shafts by using temporary steel caising in order to prevent ingress of water into the pile shafts. The average concrete volumes for single piles were approx. 20 – 24 cu. metres. Among the challenges for HCM was installation of piles in close proximity to concrete and steel underground utilities which were present on site as a result of previously demolished structure. In many cases this required coring and managing voids in the shafts after removal of these obstructions. Also, numerous piles were belled in soils with occurrence of large boulders which required special considerations for handling of equipment, customized tooling requirements and operating skills.

HCM finished foundation piling scope of work ahead of planned schedule.

Client: Cana Management
Location: Calgary, Alberta

Centron Business Park Retaining Wall

Centron Business Park Retaining Wall

Steep Slope Retaining Wall The site topography presented the developer with the challenging task of constructing a permanent retaining wall structure into a hill formation near Blackfoot Trail in southeast
Read More

Pixel by Battistella

Pixel by Battistella HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was
Read More

Alloa Feedermain

Alloa Feedermain This project involved installation of 3 watertight caisson wall shafts. Two rectangular secant pile wall shaft approx 12m deep and one 6m diameter compression ring shaft approx 7m
Read More

Talbot Street

Talbot Street HCM completed the design-build shoring for the Azure condominium project in downtown London. Due to the soil conditions encountered during initial drilling, a full depth caisson wall was
Read More
Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More

Oshawa Mall

Oshawa Mall The Oshawa Mall expansion was a large project that required several foundation and shoring services. HCM met the needs of the contractor by providing both tied back and
Read More