Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used soldier piles and shotcrete lagging shoring (SPLS) with soil nails to support the excavation of an approximately 30-foot deep underground parking garage.

One challenge of this project was the close proximity of the excavation to the property line of the adjacent residential buildings. The consultant’s design included a caisson wall for this part of the system. HC Matcon proposed an alternative to save the owner and general contractor money, schedule time, and square footage of finished building by applying an equivalent system of shotcrete shoring and soil nails. This system will also act as a one-sided form for foundation walls.

During this project, there were some unforeseen obstacles for the shoring installation that required avoidance.

Utilities were found between the shoring system and the adjacent existing building footings to be demolished. HC Matcon was able to modify the pile design to support these utilities during demolition.


Other concrete obstructions were avoided by using an alternative pipe pile design to satisfy property line constraints, a perched walkway for the access of neighboring houses, and to facilitate the demolition of the existing parking garage.

HC Matcon will take on many challenges related to shoring and foundation design while keeping the interests of the general contractor and owner in mind.

Client: Lewis Build Corporation
Location: Toronto, Ontario

BRT Tomken Station

BRT Tomken Station The Mississauga Bus Rapid Transit (BRT) project is a dedicated roadway for bus travel. It stretches 18 km from Winston Churchill Boulevard to Renforth Drive. HCM’s scope
Read More

8 Ida Street

8 Ida Street HC Matcon was retained to install panel underpinning for a custom home built by Laureden Inc. in 2007 in one of Markham’s prestigious neighbourhoods.  Due to lack
Read More

Pixel by Battistella

Pixel by Battistella HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was
Read More
Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM
Read More

Dufferin Jog Elimination

Dufferin Jog Elimination This project involved the extension of Duffering Street under an existing CN rail line and through the abutment wall of a century old CN bridge at Queen
Read More
Wal-Mart Micropiles

Wal-Mart Micropiles

Overcoming Poorly Engineered Fill This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill. The previous winter