Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used soldier piles and shotcrete lagging shoring (SPLS) with soil nails to support the excavation of an approximately 30-foot deep underground parking garage.

One challenge of this project was the close proximity of the excavation to the property line of the adjacent residential buildings. The consultant’s design included a caisson wall for this part of the system. HC Matcon proposed an alternative to save the owner and general contractor money, schedule time, and square footage of finished building by applying an equivalent system of shotcrete shoring and soil nails. This system will also act as a one-sided form for foundation walls.

During this project, there were some unforeseen obstacles for the shoring installation that required avoidance.

Utilities were found between the shoring system and the adjacent existing building footings to be demolished. HC Matcon was able to modify the pile design to support these utilities during demolition.


Other concrete obstructions were avoided by using an alternative pipe pile design to satisfy property line constraints, a perched walkway for the access of neighboring houses, and to facilitate the demolition of the existing parking garage.

HC Matcon will take on many challenges related to shoring and foundation design while keeping the interests of the general contractor and owner in mind.

Client: Lewis Build Corporation
Location: Toronto, Ontario

Canada Post Micropiles

Canada Post Micropiles

No Emissions, No Problem The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More
CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More

Brantford General Hospital

Brantford General Hospital This innovative project represents the first use of shotcrete shoring in place of caisson walls against a building in Ontario. Caisson walls have typically been utilized duw
Read More
Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2

Siemens Energy Blade Plant – Phase 2 HC Matcon’s project at the Siemens Energy Blade Plant consisted of the design, supply & installation of 70 helical piers within the existing
Read More

McMaster Nuclear Building

McMaster Nuclear Building The nuclear research building was an upgrade to the existing structure to allow for world class nuclear research for leading nuclear scientists.  This project was funded by
Read More