Skip to content

University of Toronto Faculty of Law

TTC Steels Launch Shaft

The expansion of the Faculty of Law building at the University of Toronto incorporated the addition of another storey to the existing building. The increased loading required an upgrade to the capacity of the building foundation. HCM proposed an innovative solution to install micropiles next to the caissons to accommodate the additional loading. The micropile foundation was designed by RWH Engineering Inc. (RWH), an HCM Group company.

Specialty equipment was required to install the micropiles inside the existing building, as there was only four meters of headroom in some areas. HCM used a low head room drill to install micropiles to depths of 18 meters. The micropile design required triple post-grouting to achieve the necessary bond between the grout and the soil. The soil encountered was comprised of layers of sand, silt, and clay. To confirm the design adhesion, a sacrificial load test was performed to 250% of the ULS load.

This project is an example of how HCM/RWH can offer alternative foundation solutions to meet the needs of any project, including projects with challenging site restrictions.

Client: Eastern Construction

Location: Toronto, Ontario

EEEL University of Calgary

EEEL University of Calgary

Zero Ground Loss This project followed shortly after finishing the Taylor Family Digital Library project, which was in close proximity to this site on the same campus. Design considerations for
Read More
Telus Sky tower - HC Matcon

Telus Sky tower

Telus Sky tower The Telus Sky tower will be the 3rd tallest building in Calgary with the deepest basement excavation in western Canada. HCM Group took on the challenge of
Read More

Pixel by Battistella

Pixel by Battistella HCM was contracted to provide the design and installation of shoring system for a 110 unit building consisting of town homes, studios and condos. This development was
Read More

Herald Block

Herald Block HCM was chosen to provide a comprehensive design-build shoring solution for Phase 1 of Brookfield Place development, which will become the tallest building in Western Canada. The excavation
Read More
St. Joseph's Health Centre Parking

St. Joseph’s Health Centre Parking

Shotcrete Reduces Costs for Owner The St. Joseph’s Health Centre is adding a new Our Lady of Mercy wing complete with three levels of underground parking. HC Matcon was responsible
Read More

The Osterberg Cell

The Osterberg Cell HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close
Read More