Skip to content

Canada Post Micropiles

No Emissions, No Problem

The Canada Post McKnight Mail Processing Centre Expansion project involved the installation of micropiles to support a renovation within the facility in northeast Calgary, Alberta. As the project was undertaken in an active mail processing facility, the execution presented a number of challenges. Due to the nature of the building, HCM had to deal with limited access and low overhead clearance.

Notably, there was a requirement that forbade any emissions within the building from operating equipment. This resulted in restrictions on the mobilizing of equipment, where fuel-powered engines could not be used. To solve this problem, the equipment was moved into place using an electric forklift. To satisfy the zero emission policy during work, a ducting system was conceived that vented the exhaust from the operating machines to the outside air via a connection through the roof of the building.

The nature of the facility also meant that work had to be conducted on weekends, when operations at the mail facility are light. HCM’s crew had to abide by security restrictions which limited access to specific parts of the building.

Despite the challenges, the project went well with HCM’s scope of work being completed in two days. To achieve the required capacity of the micropiles, post-grouting was required. Seven days after the installation, the piles were load tested to 150%.

Client: Scott Builders
Location: Calgary, Alberta

Oshawa Mall

Oshawa Mall The Oshawa Mall expansion was a large project that required several foundation and shoring services. HCM met the needs of the contractor by providing both tied back and
Read More

Twinning Tunnels

Twinning Tunnels The installation of a deep trunk sanitary sewer system in the bedrock beneath Erin Mills Parkway in Mississauga required an innovative approach for shoring manholes. For this project,
Read More
Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion

Medicine Hat Regional Hospital – New Tower Expansion The Government of Alberta and Alberta Health Services (AHS) have broken ground on this project, which will renovate and expand the hospital
Read More

Midtown Lofts

Midtown Lofts On this project, HCM in conjunction with RWH Engineering Inc. (RWH), provided the owner with a complete design-build package and precision monitoring services for an 8.5m deep temporary
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh
Read More

George Street Bridge

George Street Bridge This bridge replacement project required the drilling of two abutments consisting of a total of 32 drilled caissons in the existing creek bed. In addition to the
Read More