Skip to content

Guelph Civic Administration Complex

Complex Shoring Requires Innovative Design

Work on this site involved the supply and installation of caissons, underpinning, rock anchors, as well as both traditional soldier pile and lagging and shotcrete shoring systems.

  • Shoring designs were required to incorporate work next to the existing CN passenger rail tracks and the historical heritage buildings being developed into the new structure design.
  • Due to the nature and age of the buildings impacted by the work shoring design required flexibility of design while maintaining and adhering to the strict tolerances required by the specifications.

The combination of the shoring systems in conjunction with the design capacity for on site modifications allowed the excavation to be completed uniformly across the site and helped to accelerate the construction schedule.

Client: Urbacon Ltd
Location: Guelph, Ontario

CN Malton GO Station

CN Malton GO Station

Challenge: Build While Trains Are Running Work on the Malton GO Station in Toronto, Ontario includes improvements such as new walkways and a tunnel for pedestrian access to new platforms.
Read More

The Osterberg Cell

The Osterberg Cell HCM was contracted to provide supply & installation of O-Cell load test on the New Calgary Library project located in downtown core of the city, in close
Read More
65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More
TTC St. Clair Station

TTC St. Clair Station

Overcoming Tight Access and High Water Table Two new elevators on the east and west sides of St. Clair station were installed to allow easier access for disabled persons. During
Read More

Twinning Tunnels

Twinning Tunnels The installation of a deep trunk sanitary sewer system in the bedrock beneath Erin Mills Parkway in Mississauga required an innovative approach for shoring manholes. For this project,
Read More
Love Condos

Love Condos

Love Condos This project involved approx 41,000 sf of piles and lagging temporary shoring system. The project was broken into two phase both consisting of piles and lagging with both
Read More