Skip to content

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM mobilized 5 large diameter drill rigs and in seven and a half weeks installed 311 soldier piles (12,000 linear feet) drilled into bedrock up to 60 feet deep and approximately 620 filler piles (7,000 linear feet). The work was completed with an average of 30% downtime as drilling was carried out between two operational train tracks.

Client: KO Constructors
Location: Etobicoke, Ontario

Kidd's Creek Culvert Restoration

Kidd’s Creek Culvert Restoration

Versatile Installations Minimized Costs Work on the Kidd’s Creek Culvert Restoration project involved the supply and installation of 600 plus helical pile supports for new catch basins, man holes, culverts
Read More
Mill Pond Estates

Mill Pond Estates

Shotcrete: Low Cost and Overcoming Hillside Access Issues This 12,000 sq. ft. project involved temporary hillside shoring for a developer in Tillsonburg. The project was completed during winter months with
Read More

Mapleview Drive

Mapleview Drive The expansion of Mapleview Drive in Barrie required track protection for an existing railway overpass. HCM was retained to install a strutted piles and lagging shoring system. RWH
Read More
Graham Residence

Graham Residence

 Residential Shoring: Complex Design Requires Innovation A retaining wall was required to accommodate the architectural design for a private residence. The site topography presented the General Contractor (Builder) with the
Read More
65 Lillian Street Condominium Building

65 Lillian Street Condominium Building

65 Lillian Street Condominium Building Work on this jobsite included the excavation support system for a new condominium building located on 65 Lillian Street in Toronto, Ontario. HC Matcon used
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More