This project solved a very difficult problem for Buttcon and Walmart Canada, with the new footings settling on a poorly done engineered fill.

  • The previous winter had frozen some of the fill, and footing settlements of up to 3 inches were on-going as the steel was erected.
  • HC Matcon mobilized a Design Build solution utilizing 60 Ft. long micro piles, with special connections to the already designed footings and piers. Sacrificial steel design was used to provide low cost micro piles.
  • HC Matcon worked 7 days per week for 3 weeks to install 192 piles.

The Walmart store opened on schedule and was a technical success. HC Matcon is innovative when problems occur, working with owners and General Contractors to find the most economical solution.

Client: Buttcon Ltd
Location: Rexdale, Ontario

Scarborough Hospital

Scarborough Hospital

A Design-Build Solution The Scarborough Hospital was adding a new Critical Care Centre in the courtyard surrounded on all sides by existing hospital structures.  HC Matcon’s scope of work included:
Read More
Niagara Biosolids Facility - Inside Pit

Niagara Biosolids Facility – Inside Pit

A Shotcrete Solution to a Difficult Problem Work to the existing Biosolids Facility required the installation of deep pits and foundations for proposed processing equipment. Due to the tight confines
Read More

University of Ottawa STEM Complex

University of Ottawa STEM Complex HCM installed a 36,000 SF shoring system for the new STEM Complex at the University of Ottawa. To reduce the shoring schedule during the harsh
Read More
London Mental Health

London Mental Health

London Mental Health – Structural Shotcrete HC Matcon completed a 1,650ft2 structural shotcrete wall in just two days of shooting concrete. The wall had a depth of 0.450m thickness and
Read More

TTC Steels Launch Shaft

TTC Steels Launch Shaft The TTC tendered the Steeles Launch Shaft project as part of the much needed Shepherd subway extension into Vaughan. HCM undertook this project as a general
Read More
Centre 10

Centre 10

Centre 10 Two attempts had been made by others to build two high-rise condo towers on the site of the former Gaslight Square retail strip at 10th Ave and 4th